American Journal of Civil Engineering and Architecture. 2019, 7(3), 128-134
DOI: 10.12691/ajcea-7-3-2
Open AccessArticle

Calcined Termite Hill Clay Powder: As Partial Cement Replacement in Production of C-25 Grade Concrete

Guyo Konso Danbala1, , Emer Tucay Quezon2, and Getachew Kebede3

1Civil Engineering Department, Bule Hora University, Bule Hora, Ethiopia

2Department of Construction Engineering & Management, Institute of Technology, Ambo University, Ambo, Ethiopia

3Jimma Institute of Technology, Jimma University, Jimma, Ethiopia

Pub. Date: May 04, 2019

Cite this paper:
Guyo Konso Danbala, Emer Tucay Quezon and Getachew Kebede. Calcined Termite Hill Clay Powder: As Partial Cement Replacement in Production of C-25 Grade Concrete. American Journal of Civil Engineering and Architecture. 2019; 7(3):128-134. doi: 10.12691/ajcea-7-3-2

Abstract

Cement is one of the components of concrete plays a great role in the construction industry. Nevertheless, it is the most expensive and environmentally unfriendly material. Therefore, requirements for economical and more environmentally-friendly cementing materials have extended interest in other cementing materials that can be used as partial replacement of the ordinary Portland cement. This research was, conducted to examine the suitability of calcined termite hill clay powder as a cement replacing material in the production of C-25 grade concrete as a relief for this problem. The Termite Hill Clay sample was collected from Bokuluboma vicinity. The sample was calcined at the temperature of 650°C using muffle furnace, ground to the fineness of 150 µm and its chemical composition was investigated. Normal consistency and setting time of the paste having Ordinary Portland Cement and calcined termite hill clay powder from 0% to 40% replacement in 5% increment percentage investigated. The compressive strength of eight different concrete mixes with the CTHCP replacing the ordinary Portland cement prepared for 22MPa and 34MPa (i.e., for 7th and 28th days targeted compressive strength) concrete with water - cement ratio of 0.5 and 360kg/m3 cement content. The properties of the mixture assessed both at the fresh and hardened state. Results revealed that calcined termite hill clay powder found pozzolanic and can partially replace cement. It has shown that up to 11.3% replacement of the ordinary Portland cement by CTHCP, the cubes achieved a target mean compressive strength of C-25 grade concrete at 28th day 34Mpa. Although, the replacement percentage greater than 11.3% of the cement of calcined termite hill clay powder in the concrete has shown a slightly lower compressive strength. Moreover, the mix indicated workable up to 25% replacement percentage and also the setting time of the paste containing calcined termite hill clay powder found faster than that of the control mix. Hence, it is concluded that CTHCP was suitable to replace cement partially with 11.3% replacement of cement by calcined termite hill clay powder as the optimal percentage of the production of C-25 grade concrete. The fresh concrete mix was workable up to 25% replacement, and the mineral admixture served as an accelerator which is suitable for cold weather concreting works.

Keywords:
concrete grade C-25 partial replacement calcined termite hill clay powder workability compressive strength initial and final setting time.

Creative CommonsThis work is licensed under a Creative Commons Attribution 4.0 International License. To view a copy of this license, visit http://creativecommons.org/licenses/by/4.0/

References:

[1]  Sasturkar P.J., FRC – A New Sustainable Option for Construction to Mitigate Earthquakes, World Academy of Science, Engineering and Technology, (2011), 73, 926-931.
 
[2]  Naik T.R. And Moriconi G., Environmental-friendly, durable concrete made with recycled materials for sustainable concrete construction, University of Wisconsin-Milwaukee, 2006.
 
[3]  Ahmad Hadri Husain, Noor Faisal Abas, (2015). The Implantation of Waste Concrete Ash As Partial Cement Replacement Materials In Concrete. Australian Journal Of Basic And Applied Sciences. AJBAS-0007.
 
[4]  Rehan R. and Nehdi M., Carbon dioxide emissions and climate change, policy implications for the cement industry, Environmental Science & Policy, 8 (2005), 105-114.
 
[5]  Biruk Hailu, Bagasse ash as partial cement replacing materials, Master Thesis, Addis Ababa Institute of Technology, December 2011.
 
[6]  Juenger, M.C.G., Provis, J.L., Elsen, J., Matthes, W., Hooton, R.D., Duchesne, J., Courard, L., He, H., Michel, F., Snellings, R., De Belie, N., 2012. Supplementary cementitious materials for concrete: characterization needs. Mater. Res. Soc. Symp. Proc. 1488, 1-15.
 
[7]  Meshack, Charles K., Zachary A, Master of Science in Construction Engineering& Management student, Faculty of Sustainable Materials Research &Technology Centre (SMARTEC), Jomo Kenyatta University of Agriculture& Technology-Kenya (Jan.2015).
 
[8]  Wirth, R., Herz, H., Ryel, R. J., Beyschlag, W., &Hölldobler, B. (2013). Herbivory of leaf-cutting ants: a case study on Atta colombica in the tropical rainforest of Panama (Vol. 164). Springer Science and Business Media.
 
[9]  Wafa M., Themeur M., Basma S., and Med J.R., (2012). Effects of the secondary minerals on the pozzolanic activity of calcined clay: Case of quartz, IJRRAS 12(1).
 
[10]  Chakchouk, A., Samet, B., &Mnif, T., (2006). Study on the potential use of Tunisian clays as the pozzolanic material. Applied clay science, 33(2), 79-88.
 
[11]  Eugene A, (2014), Influence of mineral admixtures on essential properties of ternary cement blends; Journal of civil engineering and architecture, Vol 8, No.10 pp. 1221-1225.
 
[12]  Anigbogu, N. A. (2011). Framework for efficient development and application of pozzolan cement in Nigeria. Proceedings of nbrri stakeholders' forum, Abuja, 24th – 25th May 2011. Lagos: University of Jos.
 
[13]  ASTM C 150,'' Standard specification for Portland cement''.
 
[14]  ASTM C136 / C136M - 14 ''Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates''.
 
[15]  ASTM C1602 / C1602M - 12 ''Standard Specification for Mixing Water Used in the Production of Hydraulic Cement Concrete''.
 
[16]  Torres S, M, Barbosa NP, Lima SJG, Silva AB. A study of the Brazilian northeast laterite as cement replacement materials. In: Swamy RN, editor. Infrastructure regeneration and rehabilitation, improving the quality of life through better construction – a vision for the next millennium. Proceedings of the international conference. University of Sheffield; 28th June–2nd July, 1999. p. 297-305.
 
[17]  ASTM C187 – 11 ´ 1 Standard Test Method for Amount of Water Required for Normal Consistency of Hydraulic Cement Paste.
 
[18]  ASTM C191 ''Test Methods for Time of Setting of Hydraulic Cement by Vicat Needle.''
 
[19]  ASTM C204 - 11 ''Standard Test Methods for Fineness of Hydraulic Cement by Air-Permeability Apparatus''.
 
[20]  ASTM C33 / C33M - 18 ''Standard Specification for Concrete Aggregates''.
 
[21]  Abebe Dinku, Construction Materials Laboratory Manual, Addis Ababa University Printing Press, June 2002.
 
[22]  Augustine Uchechukwu Elinwa, (2005). Strength development of termite mound cement paste and concrete. Journal Of construction and building materials. ELSEVIER, Vol.184.
 
[23]  Wang L, Seals RK, Roy A. Investigation of utilization of amorphous silica residues as supplementary cementing materials. Adv. Cement Res 2001; 13 (2): 85-9.